Seven Mile Hill Windfarm
Energy Transportation was contracted for the complete erection & mechanical completion of 79 GE 1.5MW Turbines. Erection began September 16 and was complete on November 13 with 19 wind/weather days accounted for. This project was delayed 2 months for permitting issues. Energy Transportation ran 24 hours a day, seven days a week to complete the project on time.
Energy Transportation personnel working on the project were 158 millwrights, ironworkers, operators, laborers, safety, quality control and management team members at the height of the construction cycle.
Energy Transportation equipment used:
- Two Manitowoc 16000's
- Manitowoc 999
- Manitowoc 14000
- Manitowoc 10000
- Grove GMK 5240
- Grove RT 890
- Grove RT 880
- Two Grove RT 860's
- Grove RT 600
- Grove TMS 875C
- Grove TMS 900E
- Eight Tele-handlers/Skid Steers
- Two CAT IT38G's
|
|
|